For each affected workpack, replan will:

  • Set the replan indicator on the workpack to true.

  • If the deliverables frozen indicator is set to true, it is set to false.

  • If present, the forecast start date is copied to the replan start date, else the plan start date is copied.

  • If present, the forecast end date is copied to the replan end date, else the plan end date is copied.

  • If present, the construction start date is copied to the replan construction start date.

  • If present, the construction end date is copied to the replan construction end date.

  • For each production step for each affected deliverable:

    • if the production step has an actual date, then copy it to the replan start date, else

    • if the production step has a forecast date, then copy it to the replan start date, else

    • copy the production step’s plan date to the replan date