To change the replan dates for a deliverable:
-
While in replan mode, right-click the deliverable in the Desktop Client, and click Update Progress in the shortcut menu.
-
Select the replan dates.
-
The default replan dates are based upon the actual dates provided for steps. If an actual date does not exist for a step, the replan date will be based on the forecast date of the step. If a step has no forecast date, the replan date is based on the plan date.
-
These dates must fall within their Replan Start and End dates for the workpack.
-
The replan dates do not have to obey the time string that is set for the current deliverable. When the replan is accepted, the system will create a new time string if necessary.