To register a tag for progress:
-
Create the tag class (or expand an existing one), and then make the class realize the interfaces that can be progressed. These interfaces are:
ISPFPrgProgressItem plus either ISPFPrgDesignItem or ISPFPrgActivity.
-
Plan dates must be set during registration. However, only the plan date for the first production step can be entered by the user; the remaining plan dates are calculated based upon the step durations.
-
Actual dates and progress percentages are not enterable.
-
Only the forecast date for the first production step can be entered by the user; the remaining forecast dates are calculated based upon the step durations.
-
When registering multiple activities, they must be of the same deliverable type, and hence share the same review and return periods, and therefore use common step durations.