Allows you to add a step that will be part of the lifecycle of the deliverables associated with a workpack.
This dialog box appears when you click either the Before or After button on the Steps tab of either of the following dialog boxes:
Name - Specifies the name of the new step.
Description - Provides a brief description of the step.
Weighting - Indicates the allocated weighting of the production step. This value is a percentage, and the sum of all of the weightings for all of the steps in a workpack must equal 100.
Construction Step - Specify whether this step must be completed during the construction period (between the Construction Start and Construction End dates).
Events - Opens the Step Events dialog box, where you can define events that constitute all or some part of this step.