The Run Rollup routine provides the ability to calculate and store aggregated progress at each level of the progress reporting hierarchy.

The Run Rollup command uses the information defined for every deliverable in every workpack that is included in the rollup to calculate the current level of completion of each workpack (when applicable) and consequently the level of completion of that particular configuration.

Once the roll-up has been performed, the information is stored for that particular cut-off date, and the information is available for viewing through the View Progress user interface.

Progress is calculated at every level of the hierarchy, including every deliverable associated with every workpack, so for larger sets of data, this process may take some time.