Activity item review and return date calculation - SmartPlant Foundation - IM Update 46 - Help - Hexagon

SmartPlant Foundation Help

Language
English
Product
SmartPlant Foundation
Search by Category
Help
SmartPlant Foundation / SDx Version
10
SmartPlant Markup Plus Version
10.0 (2019)
Smart Review Version
2020 (15.0)

Setting return dates

The planned return date for an activity deliverable is calculated by adding the actual receipt date to the internal review period and the external review period.

The due date for an activity deliverable is calculated by adding the return date to the return period.

The activity return dates are set using the Manage Activity Item Dates command. See Update activity item dates for more information about setting these dates.

These dates are calculated as follows:

  • Planned return date (date to return the deliverable to the supplier) = actual receipt date + internal review period + external review period

  • Due date (date due back from supplier) = actual return date + return period

Setting return status codes

The return status of a deliverable is set by the user as the deliverable is received and checked. The user can use the Update Progress command to update the return status. Other options include configuring a dedicated update command, or configuring a workflow to update the item's progress dates. See Workflow template configuration for more information about configuring workflow steps to set return dates for a deliverable.