Submit schedule of values to the contractor.

You must submit the schedule of values to the contractor for approval to be able to track progress against the SOV items.

  1. Click Contract Scope - Schedule of Values on the menu.

  2. Edit the schedule of values so that they meet your requirements.

  3. Click Save.

  4. Click Submit.

    The schedule of values is submitted to the contractor and cannot be changed.