Submit schedule of values to the contractor.
You must submit the schedule of values to the contractor for approval to be able to track progress against the SOV items.
-
Click Contract Scope - Schedule of Values on the menu.
-
Edit the schedule of values so that they meet your requirements.
-
Click Save.
-
Click Submit.
The schedule of values is submitted to the contractor and cannot be changed.