Accept and sign the COR - Intergraph Smart Materials - Version 10.1 - Help - Hexagon PPM

Intergraph Smart Materials Portal Classic Help (10.1)

PPMProduct
Intergraph Smart Materials
aSubProduct
Portal Classic
PPMCategory_custom
Help
Version_SPMat_custom
10.1
  1. Click Change Management - Change Order Request on the menu.

  2. Select an approved change order request on the My Change Order Requests panel.

  3. Click Authorization.

  4. To accept the COR, select I agree to the scope of work, and click Save. The status of the COR is set to Accepted by Subcontractor

  5. Click Sign & Submit.

    The eSignature certification statement is displayed.

  6. Select I agree to the above statements.

  7. If a secret question and answer was defined, answer the question.

  8. Click Submit.