The Schedule of Values page allows you to populate the schedule of values (SOV) information from the agreement. Then you can edit and submit the SOV to the contractor for approval. After approval you can track progress against the SOV.

The Schedule of Values page is only available for agreements of type Subcontract with payment type Schedule of Values.