Edit milestone progress details - Intergraph Smart Materials - Version 10.1 - Help - Hexagon

Intergraph Smart Materials Portal Classic Help (10.1)

Language
English
Product
Intergraph Smart Materials
Subproduct
Portal Classic
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.1

To track the milestone progress, you must edit the detail information.

  1. Click Progress and Payment - Milestone Progress on the menu.

  2. Select a period progress number that is not submitted.

  3. Select the Details tab.

    The progress payment events assigned to the agreement are displayed.

  4. Optionally, enter the date when this activity is planned to start in the Forecasted Start cell.

  5. Optionally, enter the date when this activity is planned to be completed in the Forecasted End cell.

    The forecasted start and forecasted end dates trigger the calculation of the expected progress percentage.

  6. Type the percentage of progress of this activity for this period in the Actual Progress (%) cell.

  7. Alternatively, type the progress value for this period in the Actual Progress Value cell.

    If you enter the actual progress percentage, the actual progress value is calculated, and vice versa.

  8. When the activity has been completed within the period, enter the date of completion in the Actual End Date cell.

  9. Optionally, assign an account code to this activity in the Account Code cell.

  10. Click Save.