Move package items from one preliminary package to another preliminary package - Intergraph Smart Materials - Version 10.1 - Help - Hexagon

Intergraph Smart Materials Portal Classic Help (10.1)

Language
English
Product
Intergraph Smart Materials
Subproduct
Portal Classic
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.1
  1. On the Packing tab, select the agreement number for which you want to move preliminary package items and click Preliminary Packing Lists.

  2. Click Expand packing_expandfor the preliminary packing list (PPL) that contains the preliminary package items that you want to move. The preliminary packages for the selected PPL are displayed below.

  3. Click to select the preliminary package that contains the item(s) that you want to move to a different preliminary package.

  4. Click the Package Items tab.

  5. Select the package items that you want to move to a different preliminary package.

    Click Move Package Item(s) Move_Pre_package_item and select the target preliminary package.

    • You can move package items to another preliminary package in the same or a different PPL, which is not submitted or approved. The target PPL must have the same forecasted delivery date, delivery designation, delivery place, Incoterm and routing method as the selected package items.

    • You can also move the package items to a new package, by selecting New Package from the list. This will automatically create a new package.