How is duration calculated? - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Intergraph Smart Construction Help (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10

Duration is calculated for each selected IWP using the formula:

Duration = (Planned Hours) / (Crew Size * Hours Worked Per Day)

The Planned Finish date is updated based on the formula:

Planned Finish Date = Planned Start Date + Duration

For more information, see Calculate duration.