  • To use the Planned Man Hours vs. Actual Man Hours dashboard item, you need the following data configured:

    • Components need to be added to IWPs.

    • The components in the IWP need to have planned man hours or actual man hours.

    • The IWP must have a planned or actual finish date scheduled.

  • To use the Crew Load dashboard item, you need the following data configured:

    • You must have a crew with a crew size assigned to your IWP.

    • The IWP must have a planned or actual finish date scheduled.