When should I refresh work steps in the Rules of Progress Utility? - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Intergraph Smart Construction Help (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10

You should refresh work steps in the Rules of Progress Utility to refresh data for a specific group of components. For example, you can select to refresh work steps for a group of components based on specific property or based on component category.

When you refresh work steps in the Rules of Progress Utility, the latest rules of progress data is loaded based on the XML file the utility is reading. The following can occur:

  • All work steps already associated with IWPs are refreshed.

  • New work steps are added to the system, but they are not added to any IWPs. They can be planned in IWPs.

  • Any unplanned work steps are also refreshed. They can be planned in IWPs.

For more information, see Refresh work steps in the Rules of Progress Utility.