Select a Standard Installation Detail (SID) for a component - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Intergraph Smart Construction Help (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10

  • When you select a SID for a component, the SID is added as a work step.

  • The man hours of the work step is calculated by multiplying the rate of the SID and unit of the component.

  • SIDs can be configured to automatically associate with components when rules of progress data is generated. For more information, see Configure SID work steps to automatically associate with a component.

  1. Click Work Packages on the project home page.

  2. Select an IWP from the Work Packages browser.

  3. Click Components on the open IWP to view components.

  4. Click Expand or double-click a component name to view associated work steps. You can also double-click a component name to expand.

  5. Click Add step.

  6. Click the arrow on the text box to display Select SID.

  7. Click Select SID to open the Select SID dialog box.

  8. Select a component category from the list to display the SIDs for a particular component category, or select All to display all SIDs available for your project.

  9. Select a SID from the list.

    Click Open in a New Window to display the associated SID file. Files types supported by SmartPlant Foundation are displayed.

  10. Click Select to add the SID to the component.

    Once a SID is added to an IWP, you can click Open in a New Window to display the associated SID file. Files types supported by SmartPlant Foundation are displayed.

    Associated SID files are added to the IWP Summary and Scorecard reports.

See Also

View and report completion for IWP components
Create and manage work packages