When is the best time to turn off the ROP queue? - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Intergraph Smart Construction Help (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10

We recommend that you turn off the ROP queue before you retrieve data in Smart Construction. After you turn off the ROP queue, you can retrieve your data in order to get all data into your project without rules of progress associated yet.

You can then load and analyze your rules of progress rate tables in the Smart Construction Rules of Progress Utility window to get an overview of what data is and is not covered in rules of progress rate tables.

For more information, see Turn the Rules Processor queue on and off.