Planned man hours must be specified for IWPs when you calculate crew size.
-
In order to calculate crew size, the Numerical Crew Size option must be selected in the Manage Crew Size by box of the Smart Construction system settings. For more information, see Configure and update system settings for Smart Construction.
Calculate crew size from an IWP
-
Open the Schedule window of an IWP.
-
Click Calculate crew size .
-
On the Calculate Crew Size dialog box, type a value in the Hours worked per day box.
-
Select Ignore non-working days to treat non-working days as regular work days when calculating duration.
When you specify non-working days, you can choose to ignore them, so the non-working day would be considered a work day. If you include them, work does not occur on a non-working day.
-
Click Calculate to calculate the crew size.
Calculate crew size from the Work Packages Schedule window
-
Click Work Package Schedule on the project home page to open the Work Package Schedule window.
-
Select one or more IWPs from the Work Package Schedule window to display the Actions menu .
Press CTRL or Shift, then select one or more IWPs in the Work Package Schedule window. You can also press CTRL + A to select all IWPs.
-
Click Actions > Calculate crew size to open the Calculate Crew Size dialog box.
-
On the Calculate Crew Size dialog box, type a value in the Hours worked per day box.
-
Select Ignore non-working days to treat non-working days as regular work days when calculating duration.
When you specify non-working days, you can choose to ignore them, so the non-working day would be considered a work day. If you include them, work does not occur on a non-working day.
-
Click Calculate to calculate the crew size.
Click the Actual/Planned toggle key to change between Planned and Actual dates on the Work Package Schedule window. Planned dates display in blue, and Actual dates display in green. When you select Planned, the Work Package Schedule window displays Planned dates for each IWP. If no planned dates are set, the window displays any Actual dates that are set. When you select Actual, the Work Package Schedule window displays Actual dates for each IWP. If no actual dates are set, the window displays any Planned dates that are set. If Planned and Actual dates are not set, the Work Package Schedule window displays start date as today's date and finish date as next day's date.