Sequence components in SmartPlant Review - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Intergraph Smart Construction Help (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10

You can export components to SmartPlant Review to animate and sequence components.

Smart Construction converts the SmartPlant Review animation time line into the component sequence for an IWP. The animation end time determines the order of components. Any components not included in the animation (including non-engineered components) are added to the end of the sequence.

Do not close the Smart Construction client.

  1. Click Work Packages on the project home page.

  2. Select an IWP from the Work Packages browser.

  3. Click Components on the open IWP to view components added to the IWP.

  4. Select Open in SmartPlant Review on the View Options list to open the Select the model to use dialog box, which lists all models for components in the IWP.

    When you filter data on the Components window column headings and report progress or open the components in SmartPlant Review, the actions apply to all components in an IWP, not just the filtered portion.

  5. Select a model from the list and click OK to open the model in SmartPlant Review.

  6. Select Create animation data to create initial animation data from the display set to use in the SmartPlant Review Sequencer. For more information, see Create initial animation data in SmartPlant Review.

  7. Click OK on the SmartPlant Review synchronization issues dialog box, if any issues are found. For more information, see Resolve SmartPlant Review synchronization issues.

  8. Select and set options to create a project in SmartPlant Review.

  9. Click OK.

  10. Sequence components in SmartPlant Review. The IWP is listed as a folder under Display Sets in the Project Manager.

    See SmartPlant Review documentation for more information.

  11. Right-click the model and select Smart Construction > Send Sequence to send the revised component sequence to Smart Construction.

  12. Click Allow to allow SmartPlant Review to update the planned start and planned finish dates to the IWP. Click Don't allow to update the sequence and restrict SmartPlant Review from updating the planned start to the IWP.

    When you sequence components in the SmartPlant Review Sequencer, the planned start and planned finish dates might change. When you click Send Sequence, SmartPlant Review updates the IWP planned start and planned finish dates with the earliest start and end dates assigned to the display sets in the Sequencer. If you have dependencies established among IWPs in the Work Package Schedule window and you update the planned start and planned finish dates, the relationship dependencies are broken.

  13. Close SmartPlant Review.

Any IWP with the Components window open can receive the component sequence from SmartPlant Review:

  • In Smart Construction, open the IWP you want to receive the sequence.

  • Select the Show in SmartPlant Review option to open the components of the IWP in SmartPlant Review.

  • Select the same model you used to sequence the components on the Select the model to use dialog box. When you open the IWP in SmartPlant Review, the components without a sequence are synchronized with the animation sequences previously recorded.

  • Select the Send Sequence command to send the sequence back to Smart Construction. IWPs that do not perform this synchronization do not update their component sequences even if sequence data exists in the current SmartPlant Review session.

See Also

Use Smart Construction with SmartPlant Review