Material can be received into a site warehouse using different methods in Smart Materials. These methods are listed below.
-
Direct receiving
-
Receiving by PO
-
Receiving by Traffic
-
Receiving by Release Note
-
Receiving by Packages
Assign a receiving status to project default ZC_STATUS. This status will be set when creating a new material receiving report (MRR). The MRR number will be generated automatically based on the pre-defined MRR rule assigned to the user. If no MRR rule was assigned, the MRR rule marked as the default will be used. The revision of a new MRR number is always 0 (zero) and will be increased by 1 automatically when an MRR revision is made.
Material can only be received in a corporate warehouse in the project owning the warehouse.