You must define progress payment events if partial payment of provided services was agreed on, based on completion of certain events, such as site set-up, foundation, and so forth. These payment events will be used to track the progress payments. You can assign progress payment events to quotes on the Prog Pay Events tab of P.30.22 Commercial Evaluation window 2.

The progress payment events can be defined on the P.10.31 Progress Payment Events screen.

To define a progress payment event, enter the event name in the Prog Pay Event field and the event descriptions in the Short Desc and Description fields.