In order to track dates and activities, you can enter information about SOW milestones.
The SOW Milestones tab is available on the following screens.
-
R.30.01 Maintain Requisitions: Window 2
-
P.30.21 Prepare RFQ
-
P.30.22 Commercial Evaluation: Window 2
-
P.30.27 Bidder Quotation
-
P.50.07 Maintain Agreements: Window 2
-
SM.20.11 Subcontract Administration
Enter SOW milestones
-
Click the SOW Milestones tab.
-
In the upper part of the tab, enter a start date, substantial completion date, and final completion date, along with associated activities.
-
In the lower part of the tab, enter interim milestone information.
-
An LOV is available in most of the fields on this tab (a calendar for the date fields or a list of activities for the activity fields).
-
You can enter actual dates on this tab. Actual dates are optional but are very helpful when tracking against an agreement.
-
You can assign only one overall SOW milestone to a requisition, inquiry, or other object.