The Start Job button starts the execution of the transfer job. Job can be initialized either by clicking Start Job button or Initialize Job button.
The progress of the job execution appears on the Progress tab as shown above.
The status of a job is shown in the Status field; the possible values are:
Status |
Description |
---|---|
NEW |
New export job, not yet started. |
RUNNING |
Export job was started and is still running. |
ERROR |
Export job was aborted due to an error. When the cause of error is cleared, the job can be started again with Start Job. |
CANCELED |
Export job was canceled by the user with Cancel Job button. |
STAGE_FINISHED |
Export job has reached the defined job goal. To re-start the job, select a higher job goal, and click the Start Job button. |
JOB_FINISHED |
Export job successfully completed. |
The stage of a job is shown in the Stage field; the possible values are listed below.
Stage |
Stage Description |
---|---|
No stage passed yet |
Export job is not yet started. |
Ready to fill interface tables |
The interface temporary tables are filled with data when the Extended Customization check box is selected on Integration->Smart 3D->Smart 3D Configurations->Data Table Configurations. The generic data table templates are created. |
Interface tables filled |
The interface tables are filled. |
Consistency Verified |
The data consistency is verified. |
Written to file |
Write the contents of the interface tables into files (XLSX). |
Bulkload done |
Bulkload the transfer files into Smart 3D. |
Bulk log analysed |
Analyze the Bulkload log file to inform Smart Reference Data which lines were loaded and which were skipped. |
Sart 3D verification passed |
Verify the catalog within Smart 3D. |
Guides imported |
Load the GUIDs back into Smart Reference Data. |
Job completed |
Synchronize the Smart Reference Data inventory of Smart 3D with the data produced by the actual job. |