ROS date is managed by expediting.
With this project default, you can control who is responsible for the Required on
Site (ROS) date on item shipments.
If the project default is set to N (default), the ROS date coming from engineering
requisition is used as the Required on Site date on item shipments in all cases.
If the project default is set to Y, the ROS date is managed by the expediter. That
is, only the first time an item shipment is created is the value taken over from the
engineering requisition. From that time on, it is maintained by the expediter and
then kept for all subsequent change orders.
-
Module(s) affected by this setting: OPI1001, P3002, P3004, P5007
-
Default value: N
-
List of Values: N/Y