Range of days for critical expediting events.

With project default ZP_RDCRITE, you define a range of days within which a critical expediting event or task has to take place. All expediting events and tasks for which a planned date but no actual date has been set and for which the critical indicator has been marked are checked against this range of days and the current date.

This default is used by screen P.70.71 Expediter Workload.

  • Module(s) affected by this setting: P7071

  • Default value: ./.

  • List of Values: ./.