This project default specifies the behavior of design change control during OMI load.

This setting only takes effect if the site qty transfer option (ZI_OMI_TSQ) is also enabled. If set to Y, OMI performs automatic cancelation of over-reserved quantities, automatic re-issuing of design change quantities to appropriate design change warehouses, and automatic logging of reservation shortages, if it encounters such situations during load of a new highest issue status position data set into a BOM node.

  • Module(s) affected by this setting: B4001

  • Default value: N

  • List of Values: N/Y