In multiple forecasting, you can select multiple projects at a time and then process forecasting.
-
Forecast methods for selected project period can be established only when the last forecast period (one less than current period) is up to date.
-
Skipping period forecasting is not recommended.
Follow the steps below to establish multi forecasting.
-
Navigate to Forecasts > Multi Project Forecast.
-
In the Project Controller Navigation Register panel, select the required project controller ID.
-
On the right-hand side, at the top of the screen, in the green parameter bar, click the ellipsis to select the required project in the below fields:
-
Project Controller - Select the project controller.
-
(Optional) Project Manager - Select the project manager.
-
(Optional) Portfolio - Select the portfolio.
-
Project Period - Select a project period.
-
(Optional) Project - Select the project.
-
-
If required, click REFRESH to update the screen.
-
In the Forecast Settings panel, select the Project Level Forecasting check boxes for the projects you want to forecast.
-
Click the Save icon.
You can proceed further to establish multi forecasting for the selected projects only when you save the selection.