To view the Project Milestone Progress Details report, perform any of the following actions.

  • View the report in the Earned Value screen:

    1. Navigate to Progress > Earned Value.

    2. Click the Reports tab.

    3. Click the Project Milestone Progress Details hyperlink. A dialog box appears with a title Project Milestone Progress Details.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Earned Value > Project Milestone Progress Details.

    2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.