Project forecast reports are available via two different menu options in EcoSys Projects:
-
From Forecast screen: To view the reports from the Forecast screen, follow the procedure below.
-
Navigate to Forecasts > Forecast.
-
At the top of the screen, in the green parameter bar, click the Project Period ellipsis to select the required project period.
-
Click the Reports tab.
-
Click the hyperlink of the required report.
-
-
From Reports menu: To view the reports from the Reports menu, follow the procedure below.
-
Navigate to Reports > Forecasts.
-
Select the required report from the menu list. The report will be generated based on the last project selected.
-