The Currency & Rates tab allows you to specify the project currency and exchange rate table for a specific project.
Project exchange rate tables must be defined for any organization that use multiple currencies.
Follow the procedure below to setup the project currency and exchange rate table.
-
In the Project Details panel, click the Currency & Rates tab.
By default, the last selected project appears in the Project ellipsis. To change the project, click the Project ellipsis and select the required project.
-
Click the Project Currency ellipsis to select the required project currency.
-
Click the Project Exchange Rate Table ellipsis to select the required project exchange rate table
-
Click SAVE.