This procedure allows you to view the time-phasing data of each cost control object in a graphical format. The graph displays the Working Forecast, Base, Balance, and Adjustment costs of the selected cost control object in a bar chart format.
-
Navigate to Forecasts > Forecast.
-
Click the Time-Phasing tab.
-
Click the Time-Phased Cost hyperlink for a required cost control object.
-
In Time-Phasing Summary or Time-Phasing Manual Details panel, click the Chart tab. The time-phasing data appears based on the selected Time-Phasing Method.
By default, the selected cost control object appears in the Project / Object ellipsis and last selected project period selected at the top of screen, in the green parameter bar appears in the Project Period ellipsis.
-
(Optional) To view the time-phasing data of a different cost control object starting from a different project period, perform the following:
-
Click the Project / Object ellipsis to select the required cost control object.
-
Click the Project Period ellipsis to select the required project period.
-
Click RUN. The time-phasing data of the selected cost control object appears starting from the selected Project Period.
-