The review of a revised New EAC and New EAC Delta is only strictly necessary at this point in the forecasting process if the project has cost control objects with Time-Phased Forecast as forecast method and costs for those cost control objects were manually spread in the time-phasing screen.
-
Navigate to Forecasts > Forecast.
-
Click the Forecast tab. The Project Forecast Summary panel displays the New EAC and New Delta EAC values.