Setup is not required for objects with a Physical % Complete progress method. However, the Physical % Complete does need to be updated each project period before earned value is calculated.

This value may be updated manually or imported. Instructions for updating Physical % Complete via an import can be found in the Import Progress Methods section above.

Manually Establish Physical % Complete Amount

This procedure allows you to enter the Physical % Complete manually. Before this value is set, the progress method must be set to Physical % Complete in the Earned Value Summary panel.

  1. Navigate to Progress > Earned Value.

  2. Click the Earned Value tab.

  3. In the Earned Value Summary panel, update the Physical % Complete for the object with Progress Method- Physical % Complete.

  4. Click the Save icon.