Establish Actual Start and End Dates - EcoSys - 2.04 - Help - Hexagon PPM

EcoSys Projects Help (2.04)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.04

Actual start and end dates may be updated manually or imported. This data is used in reports, and is also utilized when calculating earned value for project objects with a progress method of Fixed Formula 0/100 or Fixed Formula 0/50/100. The user must manually ensure that the start date for a given project object falls before the end date.