This procedure allows you to establish a forecast method manually for each cost control object. If an object has a Cost Control Level assignment, the Forecast Method column will appear in yellow background. If a forecast method is not assigned, the Forecast Method will default to Current Forecast.

When the Forecast Method is modified, always run the Refresh Time-Phased Forecast action.

  1. Navigate to Forecasts > Forecast.

  2. Click the Forecast tab.

  3. Click the Forecast Method ellipsis to select the required forecast method. The available forecast methods are listed below:

    • ACCO – AC + Open Commitment

    • CBGT – Current Budget

    • CCPI – Current CPI

    • CFCT – Current Forecast

    • EAAC – Greater of EAC or AC

    • MEAC – Manual EAC

    • METC – Manual ETC

    • MDET – Manual Details

    • MPRF – Manual Factor

    • PRJD – Project Default

    • TFCT – Time Phased Forecast

  4. Click the Save icon.

    The columns that contain data used to generate the forecast appears in a green background.