This procedure allows you to establish a forecast method manually for each cost control object. If an object has a Cost Control Level assignment, the Forecast Method column will appear in yellow background. If a forecast method is not assigned, the Forecast Method will default to Current Forecast.
When the Forecast Method is modified, always run the Refresh Time-Phased Forecast action.
-
Navigate to Forecasts > Forecast.
-
Click the Forecast tab.
-
Click the Forecast Method ellipsis to select the required forecast method. The available forecast methods are listed below:
-
ACCO – AC + Open Commitment
-
CBGT – Current Budget
-
CCPI – Current CPI
-
CFCT – Current Forecast
-
EAAC – Greater of EAC or AC
-
MEAC – Manual EAC
-
METC – Manual ETC
-
MDET – Manual Details
-
MPRF – Manual Factor
-
PRJD – Project Default
-
TFCT – Time Phased Forecast
-
-
Click the Save icon.
The columns that contain data used to generate the forecast appears in a green background.