This procedure allows you to establish percent complete by replicating the percent complete of a source object. Only one object line item may be established for an object having an Apportioned Effort progress method.
-
Navigate to Progress > Earned Value.
-
Click the Earned Value tab.
-
In the Progress Method column, click the Apportioned Effort hyperlink. The Apportioned Effort panel appears.
-
Click the Insert Row icon.
-
Click the Source Path ID ellipsis to select the object whose progress will be used to define the progress of the selected object with the apportioned effort progress method.
-
Click SAVE. The Source % Complete will be updated after the Recalculate Working Forecast process is run.
The data in the column Preview % Complete in Earned Value Summary panel is never displayed for objects with an Apportioned Effort progress method.