To view the Estimate Snapshot Summary report, perform any of the following actions.

  • View the report in the Estimate Summary screen:

    1. Navigate to Estimating > Estimate Summary.

    2. At the top of the screen, in the green parameter bar, click the Project ellipsis to view all the estimate details.

    3. Click the Reports tab.

    4. Click the Estimate Snapshot Summary hyperlink. A dialog box appears with a title Estimate Snapshot Summary.

    5. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    6. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Estimates > Estimate Snapshot Summary.

    2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.