Update Exchange Rate Table - EcoSys - 2.04 - Help - Hexagon PPM

EcoSys Projects Help (2.04)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.04

This procedure allows you to update the selected exchange rate tables to all the cost objects of the project.

  1. Navigate to Projects > Project Structure.

  2. At the top of the screen, in the green parameter bar, click the Project ellipsis to select the required project.

  3. Click Refresh for screen update.

  4. Click the Actions list, select Update Exchange Rate Table.

  5. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    The Project displayed in the green parameter bar at the top of the screen is the only project available for the selection in the Update Exchange Rate Table dialog box.

  6. Click the Exchange Rate Table ellipsis to select the required exchange rate table.

  7. Click RUN and then OK. In the Project Structure panel, the selected exchange rate table appears for all the cost objects of the project in the Object Exchange Rate Table column.

    To view the Object Exchange Rate Table column, you must customize the view of the Project Structure panel from the View Settings.