Beveling time is calculated as follows:

  • Given as one work time value per one pipe part, including both ends of the pipe, as the unit [min].

  • Based on the material diameter and thickness of the pipe.

Beveling time can be estimated e.g calculating volume of the removed material. Beveling time can include some other work times like in-feeding, preparation, out-feeding, lifting & turning, etc.