This procedure allows you to view the time-phase charts.
-
Click the TIME-PHASING tab.
-
In the Estimating Time-Phasing panel, click the Total Cost hyperlink of the estimate object.
-
In the Time-Phasing Details panel, click the CHART tab. The time-phasing data appears based on the selected Curve.
By default, the selected estimate object appears in the Project/Object ellipsis.
-
(Optional) To view the time-phasing data of a different estimate, perform the following,
-
Click the Project/Object ellipsis and select the required cost control object.
-
Click the Run icon. The time-phasing data of the selected estimate object appears.
-