Additional setup is required for the Apportioned Effort, Physical % Complete, Progress Package, Schedule Activity % Complete, Weighted Milestones, and Weighted Quantities progress methods.

After setup is complete: updates to a percentage amount (Weighted Milestones and Physical % Complete progress methods) or actual quantities (Weighted Quantities progress method) must be completed before earned value is calculated.