This process allows you to create baselines for project schedule activity.

  1. Click the BASELINE tab.

  2. Click the Actions list and select Create Baseline.

  3. Click the ellipsis for each of the below fields and select the required values:

    • Project - Select the project for which you want to create baseline.

      The project selected in the tool bar at the top of the screen is the only project available to select.

    • Baseline - Select the required baseline.

  4. (Optional) Comment - Type a comment related to the Baseline.

  5. Click RUN and then OK.

    Baselines appears under the project activity bars. They are indicated with tan color bars.