This procedure allows you to create a new estimate project using the selected estimate project as a source project. The new project contains the source project's structure and estimates transactions. After the estimate project is created, a log entry appears on the Log tab and an email notification is sent to the project creator to confirm that the project was successfully created.
-
Click the Actions list and select Create Estimate Project from Estimate Project.
-
Click the Estimate Source Project ellipsis and select the required estimate source project.
-
Type the required Project Name.
-
Click the Security Organization ellipsis and select the security organization. By default, the Organization appears.
-
(Optional) Type the Comment.
-
Click RUN and then OK.
To view the log entry, click the Project ID hyperlink and then click the Log tab in the Project Details panel.