The Validation Checks panel help you to understand if a forecast variance change is ready to be submitted for approval. You can submit a forecast variance change for approval only if all the cost control objects have been time-phased and if any submitted forecast variance changes for previous project periods have been approved. Workflow users required to approve the forecast variance change per threshold settings (see Project > Project Setup) must be defined properly as well.

You can view the status of the validation checks in the Validation Checks panel. If the Failure Count is zero, it indicates that all validation checks have passed, and the validation checks appear with green background. Otherwise, it indicates that one or more validation checks have failed, and the failed validation checks appears with a red background. If the validation check is red, error specifics are displayed in the Error Description column. Only after all the validation checks have passed (green), you will be able to submit the forecast variance change for approval.

Cost in Object Currency should be viewed only after Time-Phasing is done.

Follow the procedure below to view the status of validation checks.

  1. Navigate to Forecasts > Forecast.

  2. Click the REGISTER tab. The validation checks appear in the Validation Checks panel.