Systematic (non-manual) time-phasing is performed using the Time-Phase Unapproved Change action. This action will spread the costs, quantities, and hours based upon the line item’s Start Date, End Date, and Curve displayed in the Change Register panel, except for the following:

  • If the Current Budget curve type was selected, the Original Budget curve type associated with the Object Path ID selected will be used to drive the spread.

  • If the Current Forecast curve type was selected, the Original Forecast curve type associated with the Object Path ID selected will be used to drive the spread.

Follow the procedure below to systematically time-phase the change line-items.

  1. Navigate to Changes > Changes.

  2. Click the Actions list and select Time-Phase Unapproved Change.

  3. Click the Project ellipsis to select required project.

    The Project displayed in the tool bar at the top of the screen is the only project available for selection in the Time-Phase Unapproved Change dialog.

  4. Click the Change ellipsis to select required change.

  5. Click RUN and then OK.