Thisprocedure allows you to assign resources and update all the details related to the cost object.

  1. In the Project Scheduler panel, select the cost object row for which you want to add or assign resources.

  2. In the Project Schedule Details panel, click the RESOURCE ASSIGNMENT & RATES tab.

  3. In the Schedule Assignments panel, add new resources. There are two methods to add resources.

    Manual - In the Schedule Assignments panel, click the Insert Row icon to add a new row.

    (Or)

    Resource Rate Table - In the Resource Rates panel, click the Add hyperlink against the required resource.

    The Resource ID and resource Rate are predefined in the Resource Rate table.

  4. Click the ellipsis and select the required values:

    • Object Path ID - Select the main object path ID.

    • Cost Account ID - Select the cost account ID

    • Resource ID - Select the resource ID that you want to assign

  5. Type the values for the below attributes:

    • Description

    • Quantity

    • Hours

    • Rate (Hrs)

    • Cost

      Rate attribute updates only when Hours are entered or changed.

  6. Click the ellipsis for each of the boxes below and select the required values:

    • Curve - Select the appropriate curve

    • UOM - Select the required unit of measurement

    • Currency - Select the required currency

  7. Click the Rate Source list and select the rate source.

  8. Click SAVE. The Cost in Object Currency auto-populates.

    Click the Delete Row(s) icon to delete the selected row.