The document is revised in a tool to make additional changes. The tool manages its own revision schemes and sets the revision of the document to 5. Rather than selecting a revision scheme to match the tool revision scheme, you choose a new revision scheme.
-
In the Revision Scheme list, select RevA01.
-
In the Revise in Tool > Major list, the first major revision is A. A is the first available revision because the document has not been previously published in SmartPlant Foundation.
For a document that has been revised and published previously in a tool with a last revision of B, the first available major is B when you attempt to revise using the Revise dialog box with a compatible revision scheme, such as RevA01. You can accept B or set the revision to a higher major, such as D.