This procedure allows you to view the hours allocated to resources for a particular activity in the chart format.
The Resources Assigned must be time-phased before seeing them on this chart.
-
In the Activity Scheduler panel, select the activity row for which you want to view the resource hours chart.
-
In the Activity Task Scheduler Tabs panel, click the Resource Hours Chart tab to view the chart.
-
(Optional) Type the resource name in the Filter box to filter the resource.
-
(Optional) Click the Timescale Unit list and select the time unit.
This spreads the chart bar on the selected time unit scale.
-
(Optional) Select the Show subscale check box.
The selected subunit timescale is displayed below the timescale unit. This helps in identifying the utilization of resource for the particular activity in high-level.
-
(Optional) Click the Timescale Subunit list and select the time subunit.