View Time-Phase Charts - EcoSys - 4.01 - Help - Hexagon PPM

EcoSys Projects Help (4.01)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
4.01

This procedure allows you to view the time-phasing data for the selected project in a graphical format. The graph displays the Working Forecast, Base, Balance, and Adjustment costs of the selected cost control object in a bar chart format.

  1. Navigate to Forecasts > Multi Project Forecast.

  2. In the Forecast Settings panel, click the required Project ID hyperlink.

  3. In the Project Forecast Summary panel, click the Chart tab. The time-phasing data appears based on the selected Time-Phasing Method.

    By default, the project period selected at the top of screen, in the green parameter bar appears in the Project Period ellipsis.