This process creates a new forecast variance change. Based upon the total change value, the change may be automatically approved and posted to the Current Forecast.

Forecast Variance changes cannot be submitted for approval unless all validation checks have passed.

Follow the procedure below to create the forecast changes.

  1. Click the Actions list and select Create Forecast Change (Multi Project).

  2. Click the Project Controller ellipsis to select the project controller.

  3. Click the Project Manager ellipsis to select the project manager.

  4. Click the Portfolio ellipsis to select the required portfolio.

  5. Click RUN and then OK.