Acronyms - Intergraph Smart Materials - Version 2.0 - Reference - Hexagon PPM

Intergraph Smart Materials Enterprise Work Process for Materials Management

PPMProduct
Intergraph Smart Materials
PPMCategory_custom
Reference
Version_SPMat
2020 (10.0)
  • BOM – Bill of Materials

  • CO – Change Order

  • COR – Change Order Request

  • ERP – Enterprise Resource Planning

  • HVAC – Heating, Ventilating and Air Conditioning

  • ITT – Invitation To Tender

  • MTO – Material Take-Off

  • NTC – Notice To Comply

  • OSD – Over/Short/Damage

  • OWL – Outstanding Work List

  • PCO – Potential Change Order

  • QA/QC – Quality Assurance/Quality Control

  • RFQ – Request For Quotation

  • ROS/ RAS – Required On Site, Required At Site (same meaning)

  • VDR – Vendor Data Requirements